Two different numbers get called “what it costs to open a restaurant”, and they are nowhere near each other.
The first is the buildout: design, construction and equipment. It is the number a contractor quotes, the number our cost calculator gives you, and the number people repeat to each other. The second is what actually leaves your account between signing a lease and breaking even. On the projects we see, the second is 1.4 to 1.8 times the first.
That gap is not waste and it is not padding. It is deposits, fees, rent on an empty room, a stock of plates, three months of payroll, and the cash reserve that keeps the doors open through a slow February. Every line is predictable. The only thing that surprises people is the total.
This guide takes the buildout number and builds the rest on top of it.
The short answer
For a 2,000 to 2,500 sq ft restaurant in a second-generation space in Waterloo Region, in 2026:
| What | Planning range |
|---|---|
| Buildout — design, construction, equipment | $300,000 – $700,000 |
| Everything else | $120,000 – $550,000 |
| All in, before the first sale | $420,000 – $1.25M |
The Greater Toronto Area runs about 14 per cent higher on the construction side. A cold shell rather than a former restaurant adds roughly a third again, and a retail or office unit becoming a restaurant lands close to that, because the change of use pulls washrooms, exiting and occupant load into scope as code requirements.
Those bands are wide because the honest version is wide. Two identical square footages in the same city can differ by a factor of two on what the landlord delivered and what the last tenant left behind. Why the first number and the final number differ covers what closes that gap.
Start with the buildout, not the total
The buildout is the one part of this with a market rate, so it is the right place to anchor. For an Ontario restaurant in a second-generation space it runs $150 to $330 per square foot outside the GTA; a cold shell or new build runs $227 to $446. Add about 14% for the Greater Toronto Area on both. What a restaurant buildout actually costs in Ontario breaks those ranges down by project type and market and explains what moves them — ventilation, electrical service, plumbing and grease, and the condition of the base building.
What the band covers: the drawings and engineering, the construction, and the equipment package delivered, installed and commissioned.
What it does not cover is everything below.
The seven lines that sit on top
1. Permits, reviews and municipal fees — 0.5 to 3%
Smaller than almost everyone expects, and worth knowing precisely, because it is one of the few numbers here you can look up rather than estimate.
Permit fees are charged on the area of work, not on what you spend. Toronto’s 2026 schedule charges $12.45 per square metre for interior alterations in Group A, B and D occupancies and $11.53 for Group C, E and F, with a minimum permit fee of $214.79 and examination time beyond five hours billed at $92.79 an hour. Kitchener charges $0.37 per square foot for interior finish work and $163 for a change of use, plus a $1,000 rebate fee on commercial alteration permits — cash out at the start, refunded automatically once the inspector approves the final building inspection.
On a 2,400 sq ft fit-out, the building permit itself is roughly $900 in Kitchener and $2,800 in Toronto. Add the plumbing permit, charged per fixture, the electrical notification your contractor files with the ESA, a sign permit and a municipal business licence, and the whole statutory pile is a few thousand dollars. Every approval, in order sets out who issues each one.
The exception that is not small. Ask the building department early whether development charges apply to your project. Practice differs by by-law: some municipalities exempt a change from one non-residential use to another when no floor area is added, and others charge where the use category changes, because a restaurant’s water and sewer demand is not a shop’s. Kitchener’s own development charge form asks for existing and proposed non-residential floor area and whether a redevelopment allowance applies, which is the shape of the question everywhere. The answer is worth having before the lease, not after the permit.
2. Lease deposits and security — 3 to 8%
Payable at signing, before anything is designed. First and last month is the floor; a landlord with any doubt about a first-time operator asks for more, and some ask for a letter of credit. Read the lease for what else is pre-payable: common area maintenance, realty taxes, and the insurance the lease requires you to carry at the coverage it specifies.
This is also where a tenant improvement allowance shows up, and where its timing matters. An allowance is typically paid on completion, against conditions, so you fund every invoice yourself first and are reimbursed at the end. Your peak cash requirement is the full build cost, not the build cost minus the allowance.
3. Smallwares, tableware and opening inventory — 4 to 8%
Not construction, and it comes out of the same account: pots, pans, hotel pans, knives, sheet trays, speed racks, china, glassware, cutlery, linens, chemicals, first aid, uniforms, menus, and the first food and beverage order. Individually unremarkable, collectively a five-figure line on a restaurant of any size.
It is also the easiest line to get wrong in both directions. Buying smallwares against the finished kitchen layout rather than a wish list usually takes money out of it.
4. Rent and carry during the build — 5 to 12%
Design and permitting take four to eight weeks. Construction and equipment setup take eight to sixteen. That is three to six months of rent, interest and insurance with no revenue, and free-rent periods rarely cover a full design-permit-build cycle.
Schedule is a cost. The three most common causes of delay are an incomplete permit submission, a late menu change that forces a redesign, and equipment ordered too late against its lead time — and all three are avoidable at the planning stage, where avoiding them is free.
5. Licences, insurance, POS and pre-opening payroll — 2 to 5%
The licensing side is cheap and specific:
| Licence or certification | Fee |
|---|---|
| AGCO Liquor Sales Licence, new application with public notice | $1,055 (two years) or $1,355 (four years) |
| AGCO Liquor Sales Licence, renewal | $300 (two years) or $600 (four years) |
| Smart Serve, full online program | $44.95 per person |
AGCO fees are non-refundable if the application is withdrawn or refused, and the liquor licence comes last in the sequence because it needs building, fire and health sign-off first — the AGCO liquor licence guide covers what that application needs and when notice can be skipped. At least one person with food handler training has to be on the premises every hour you are open, so budget that course for more than one person.
What costs real money in this line is the fortnight before opening: staff hired, trained and paid while the room is still empty, plus the POS, the first insurance premium, the merchant account, and the deposits the gas and electricity utilities want from a business with no history.
6. Contingency — 10 to 15%
On a renovation, ten to fifteen per cent of the buildout, shown as its own line. Not because the estimate is bad, but because existing buildings hide things behind walls, and nobody with construction experience believes a food project hits its first number exactly.
Treat it as spent until the project proves otherwise. A contingency quietly spent on an upgraded finish in month one was never a contingency.
7. Working capital to break-even — 15 to 30%
The line that closes finished restaurants.
Three months of operating cost — rent, payroll, food cost, utilities, loan payments — in cash, separate from the build. Properly it comes out of your own operating budget rather than a percentage of a construction number; the 15 to 30 per cent band is the quick check that tells you whether what you have set aside is in the right range at all.
Opening is not the end of the spending. The costs that arrive after you open — hood and duct cleaning, fire suppression inspections, interceptor pump-outs, refrigeration service, and the energy bill your equipment choices locked in months earlier — all start on day one, against revenue that takes time to arrive.
A worked example
A 2,400 sq ft restaurant renovation in a second-generation space in Waterloo Region. The calculator returns a planning range of $360K – $670K for the buildout. Take $500,000 as the working number:
| Line | Planning range |
|---|---|
| Buildout — design, construction, equipment | $500,000 |
| Permits, reviews and municipal fees | $2,500 – $15,000 |
| Lease deposits and security | $15,000 – $40,000 |
| Smallwares, tableware and opening inventory | $20,000 – $40,000 |
| Rent and carry during the build | $25,000 – $60,000 |
| Licences, insurance, POS, pre-opening payroll | $10,000 – $25,000 |
| Contingency | $50,000 – $75,000 |
| Working capital to break-even | $75,000 – $150,000 |
| All in | $700,000 – $905,000 |
The spread between those totals is not optimism against pessimism. The low end is a disciplined project in a space that genuinely suits the menu, with a landlord contribution and a permit cycle that ran clean. The high end is the same room with a longer approval, a service upgrade nobody priced, and a cash reserve sized for a slow first quarter. Both are real outcomes, and most of what separates them is decided before construction starts.
What moves the all-in number most
What you inherit. A second-generation space with a hood that suits your menu and an interceptor sized for your fixture count is worth more than any other saving available. One that suits a different menu can erase the saving entirely.
The menu, decided early. Open-flame and grease-producing cooking means a Type 1 hood, fire suppression and make-up air; a menu that avoids it may qualify for a Type 2 and a materially smaller mechanical budget. That is a budget decision disguised as a creative one, and it has to be made before the kitchen is designed.
The lease. Free rent, the fixturing period, the allowance and who owns the improvements at the end are all negotiable, and each moves the all-in number more than anything you can shave during construction. Before you sign covers what to check.
How it is funded. The mix matters as much as the total, because the problem is usually timing rather than size. How food buildouts get paid for maps the pieces and where the cash-flow gap falls.
Where the budget usually goes wrong
- Pricing the buildout and calling it the project. It is 55 to 70 per cent of the number.
- Treating the landlord allowance as cash in hand. It arrives at the end, against conditions.
- No working capital line at all — or one that gets spent during construction.
- A contingency buried inside the construction number rather than shown separately, so drift is invisible until it is large.
- Pricing equipment before specifying it. A number without connection and commissioning is not a complete price.
Getting to your own number
A planning range is enough to test whether a deal is plausible. It is not enough for a lender or a lease.
For that, someone has to walk the specific unit: check the electrical service against your equipment load, see where the exhaust can discharge, confirm the zoning permits your use, look at the interceptor, and price the actual gap between what is there and what your menu requires. That walkthrough is our first consultation, and it costs nothing. You leave with a timeline and a cost breakdown split into design, construction and equipment — the kind of document a lender or a landlord will actually read.
Start with the cost calculator for the buildout range, then call (226) 336-9954 or email info@nhfc.ca for the rest of it. Better before you commit to the space than after.
Fees in this guide were checked against the issuing authority on 30 October 2026: Toronto Building’s 2026 fee schedule, the City of Kitchener’s building permit fees, and the AGCO’s liquor licensing fees. Municipal schedules are adjusted annually and AGCO fees are set by its board, so confirm the current figure before you budget on it.