Toronto is the most expensive market we work in and the one where sequence matters most, because two separate reviews run in parallel and either can hold up an opening.
Book a free consultationWho signs off on your project here
A food premises in Ontario needs a municipal building permit and a public health review, and they are not the same submission. In Toronto they go to these two:
Building permit
Toronto Building
Issues the permit and carries out the building inspections.
Their permit page ↗Toronto Public Health reviews building plans for new and renovated food premises, assesses the kitchen plan, and carries out the pre-opening inspection. Plans are submitted to the health unit separately from the building permit application.
Grease interceptor rules
Toronto Municipal Code Chapter 681, Sewers
Section 681-10B requires an interceptor installed to the Building Code and maintained to the City's Food Service Establishment Environmental Code of Practice: serviced every four weeks, or sooner if grease and solids reach 25 per cent of its liquid volume, with servicing records kept at the premises for seven years.
Verified against each authority's own published material between September and November 2026. Processes and requirements change, and the only answer that counts for your project is the one the authority having jurisdiction gives for your address — check each before you rely on anything here.
On the ground
Toronto Building issues the permit and Toronto Public Health assesses the food premises. They are separate submissions asking unrelated questions, and a set drawn to satisfy one is not automatically ready for the other. Running them in parallel rather than in sequence is worth several weeks.
Public health carries out a pre-opening inspection, and what is inspected is what the approved plans promised. Equipment substituted late, a sink moved on site or a finish changed for cost are the things that turn a sign-off into a return visit.
Trades, access, staging and parking all cost more here, and our model reflects it at roughly 14% above the southwestern Ontario band. Downtown units add loading and hoisting constraints that a suburban plaza never raises.
What it costs here
These are the same figures our public cost calculator uses, with its market factor for the Greater Toronto Area applied, a second-generation space assumed and all of the kitchen built new. A cold shell runs higher; an operating refresh runs lower; and inheriting a working kitchen — hood, grease interceptor, gas service, most of the equipment — takes it below the bottom of these bars.
Projects
Federally Registered Halal Meat Processing Plant
Toronto, ON · 38 weeks, blueprint to first production run
Grocery / Specialty Food Retail24-Hour Grocery in a Downtown Condominium Podium
Toronto, ON · 30 weeks, blueprint to open
Franchise Rollout — Quick-ServiceFour-Location Pizza Franchise Rollout Across the GTA
Toronto, Mississauga, Vaughan and Pickering, ON · 14 months for all four; 19 weeks for the first, 12 for the fourth
Ghost Kitchen / CommissarySix-Suite Ghost Kitchen and Shared Commissary
Mississauga, ON · 26 weeks, blueprint to open
Toronto Public Health reviews building plans for new and renovated food premises, assesses the kitchen plan and carries out the pre-opening inspection. Plans go to Toronto Public Health separately from the building permit application.
From Toronto Building. Its permit and Toronto Public Health's review are separate submissions asking unrelated questions, so a set drawn for one is not automatically ready for the other. Running them in parallel rather than one after the other saves several weeks.
Differences from the approved plans. What is inspected is what the plans promised, so equipment substituted late, a sink moved on site or a finish changed for cost are what turn a sign-off into a return visit.
Every four weeks, or before the grease and solids together reach 25 per cent of its liquid volume, whichever comes first, under the Code of Practice that Toronto Municipal Code Chapter 681 points to. The City can allow up to eight weeks if your records show the unit stays under 25 per cent in the first four. Servicing records stay at the premises for at least seven years.
Brampton
Greater Toronto Area
Vaughan
Greater Toronto Area
Markham
Greater Toronto Area
Oakville
Greater Toronto Area
Burlington
Greater Toronto Area
Oshawa
Greater Toronto Area
Hamilton
City of Hamilton
Kitchener
Waterloo Region
Waterloo
Waterloo Region
Cambridge
Waterloo Region
Guelph
Wellington County
London
Southwestern Ontario
Mississauga
Greater Toronto Area

Toronto projects
A site and lease review costs nothing and is the cheapest point at which a project can still change direction. You get a realistic timeline, a preliminary cost breakdown and the risks we can already see in the building.
Mon – Fri, 9:00 a.m. – 5:00 p.m. · No obligation