F.A.Q
Grouped by the stage they usually come up in. If yours is not here, the first consultation is free — ask us directly.
We produce the complete drawing set a municipality actually asks for: architectural floor plans, equipment layouts, reflected ceiling plans, and the mechanical, electrical, and plumbing drawings that go with them. That covers restaurants, cafés, grocery stores, bakeries, and food production facilities. The set is drawn to the Ontario Building Code from the start, so exhaust hood sizing and make-up air, plumbing fixture counts, grease interceptor placement, and barrier-free clearances are resolved on paper rather than argued about on site. You receive a stamped, permit-ready package plus the working drawings your trades build from.
Yes. NHFC is a turnkey firm, which means one team designs the space, pulls the permits, tenders and manages the trades, and oversees the build through final inspection. You are not coordinating an architect, a general contractor, an equipment dealer, and a permit expediter who each blame the other when something does not line up. Because the people who drew the hood, the gas line, and the electrical service are the same people scheduling TSSA and ESA inspections, changes get resolved in hours instead of weeks. One contract, one project manager, one accountable party at handover.
Both. A large share of Ontario food projects are renovations of second-generation space, and those carry their own problems: undersized electrical service, a hood that was never balanced for make-up air, a grease interceptor that no longer suits the menu, or washrooms that predate current barrier-free requirements. We survey what is actually there, tell you what can be reused, and design around it. New builds and cold shells get the same treatment from a blank slate. Either way, the finished space is designed and delivered to current code, not to whatever was acceptable when the building was last touched.
Design and permitting typically run four to eight weeks, covering drawings, public health unit plan review, and the building permit application. Construction and equipment setup typically run eight to sixteen weeks depending on square footage, how much mechanical and electrical work is involved, and whether the space is a cold shell or a second-generation restaurant. Those windows assume the landlord’s base building is ready and that decisions come back promptly. The most common causes of slippage are late menu or equipment changes and slow municipal review cycles, both of which we plan around rather than discover late.
A Type I hood is for grease-laden vapours — anything fried, grilled, broiled or charbroiled — and carries filtration, a fire suppression system and its own cleaning regime. A Type II hood handles heat, steam and odour only, over equipment such as dishwashers or some ovens. Putting Type II over a fryer is a serious fire and code problem, and which one you need is decided by the appliance line you actually install, not the one the previous tenant had.
If you are exhausting a commercial kitchen hood, yes. Air pulled out has to be replaced, and without a make-up air unit the space goes negative — doors become hard to open, the hood stops capturing properly, and in the worst case combustion appliances backdraft. Make-up air is frequently underestimated in early budgets because it is a second, separate rooftop unit with its own gas, power and structural requirements.
This is the question worth answering before signing anything. What matters is the incoming gas service and meter capacity, and the amperage actually available at your panel — not what the listing says. Upgrading either means involving the utility, and that is measured in months and can cost more than the equipment it was meant to feed. Every appliance carries a gas and electrical requirement; add them up against the building before you commit. Power and gas for a commercial kitchen sets out what to check on a panel label and a gas meter, and what the numbers mean.
It has to be smooth, non-absorbent, slip-resistant and cleanable, and it has to be coved where the floor meets the wall so there is no square joint to trap soil. That usually means a resinous or urethane-cement system, or commercial sheet vinyl with a welded seam — not tile with standard grout in the wet areas. The floor also has to go in at the right point in the sequence, because trades that follow it will damage a finish laid too early.
It depends far more on menu and service style than on seat count. A pizza takeout and a full-service kitchen producing the same covers need very different back-of-house. Rather than a percentage rule, work back from the equipment line your menu requires, then add the clearances, the aisles, the dish area, dry storage, refrigeration and the staff facilities. A layout that fits the equipment but not the people working around it fails at inspection and in service. Commercial kitchen layout covers the aisle and clearance dimensions that decide what actually fits, and the back-of-house rooms most plans leave out.
Yes, and it is one of the reasons owners hire us. We prepare and submit the full application package to the city and to your local public health unit, then coordinate directly with plans examiners, health inspectors, and the fire prevention office until approval lands. That includes the building permit, the food premises plan review, and the sign-off trail for gas appliances through TSSA and electrical work through ESA. We track every comment letter and resubmission so nothing sits waiting on an unanswered question. You get status updates rather than a stack of forms.
Complex requirements are normal in food service, not an exception. Open-flame cooking drives Type 1 hood and fire suppression design, make-up air balancing, and fire separation details. High-volume prep drives handwash sink placement, finish schedules, and grease interceptor sizing under the local sewer-use by-law. We work with licensed engineers and certified inspectors on the mechanical, electrical, and fire suppression scope so the design satisfies the Ontario Building Code, the Fire Code, and your public health unit before it goes for review. Difficult conditions are engineered around, not discovered during a failed inspection.
We do. Before a lease is signed we run a zoning review to confirm the unit permits a restaurant, take-out, or food processing use, and to flag parking, patio, and exhaust discharge conditions that come with it. If the space was previously retail or office, the project needs a change-of-use application, which usually triggers a fresh look at occupant load, exiting, washroom counts, barrier-free access, and fire separations. We prepare that submission, carry it through review, and close out the occupancy permit. Catching a zoning conflict before you commit to a lease is the cheapest fix available.
Review timelines belong to the municipality and the public health unit, and no consultant controls them. What we control is everything that causes delay. Most lost time comes from incomplete submissions, drawings that contradict each other, or a comment letter that sits unanswered for two weeks. We submit complete packages the first time, sequence the building, health, gas, and electrical approvals so they run in parallel where possible, and respond to reviewer comments within days. Familiarity with how individual Ontario offices process food premises applications keeps a project moving through the queue rather than stalling in it.
Usually yes. A permit is triggered by the work, not by the previous use — new plumbing, a new hood, moving a wall, changing the electrical service or altering the exiting all require one, and almost every food fit-out does at least one of those. Taking over a unit and changing nothing but the sign is the rare exception. Separately, the health unit has to review the premises even when the building department does not, so “no building permit” never means “no approvals”.
A change of use is when a space moves from one occupancy classification to another — retail or office becoming a restaurant, for example. It matters because it pulls washroom counts, barrier-free access, exiting and occupant load into scope as code requirements rather than design choices. Those are the items most likely to add cost late, so they are worth settling during feasibility, before a lease is signed and long before anything is drawn.
Plan on four separate fixtures: a multi-compartment warewashing sink, a dedicated hand-washing sink within reach of each food-prep area, a food-prep sink, and a mop or service sink. Sink count and placement is the single most common reason a plan review comes back with comments. The exact requirement is set by your public health unit for your layout and menu, so confirm it with them before the drawings are finalised rather than after.
If you produce grease-laden wastewater, almost certainly — and the size and type are set by the municipal sewer-use by-law, not by the building code, so it genuinely differs between Toronto, Peel, Waterloo Region and London. Retrofitting one into a finished floor is one of the more expensive surprises in a food buildout, so it belongs in the drawings from the start. See the dish area for how it sits alongside the rest of the drainage design.
Two separate authorities, asking unrelated questions. The municipal building department inspects the construction — structure, plumbing, gas, electrical, fire separation — through a sequence ending in occupancy. Public health inspects the food premises itself: surfaces, sinks, food flow, refrigeration and the equipment you actually installed against the plans you submitted. Passing one does not release the other, and both have to clear before you can trade.
No, and doing it is how projects lose months rather than save them. Work done without a permit can be ordered opened up for inspection or removed, and a building department that finds unpermitted work tends to look harder at everything else. The legitimate way to compress a schedule is to run the building permit and the public health review in parallel and to order long-lead equipment early, not to start swinging hammers.
Yes. We source through established Canadian and North American suppliers covering cooking lines, refrigeration, dishwashing, bakery equipment, food production machinery, and front-of-house fixtures. Because we design the space and buy the equipment, the spec sheet and the drawings agree: utility rough-ins, clearances to combustibles, hood coverage, and drain locations are set from the actual model being installed rather than a generic allowance. That avoids the classic problem of a fryer arriving with a gas connection the plumber never roughed in. We can also work with equipment you already own or have sourced elsewhere and design around it.
Installation is part of the scope. We schedule delivery to match construction so equipment is not sitting in a finished dining room for a month, then handle rigging, placement, levelling, and connection to gas, electrical, water, and drainage. Gas-fired appliances are connected and commissioned by licensed technicians for TSSA sign-off, and electrical connections are completed for ESA inspection. Hoods are balanced with make-up air, refrigeration is charged and temperature-logged, and every unit is tested under load before handover. You also get the manuals, warranty registrations, and a walkthrough with your kitchen staff.
We specify only commercial-grade equipment from manufacturers whose units carry the certifications Canadian authorities look for: CSA or equivalent electrical and gas approval for the Canadian market, and NSF or equivalent sanitation listing for food-contact surfaces. Residential-grade appliances and grey-market imports without a Canadian certification mark are a common reason projects fail inspection, and we do not put them in a kitchen. Certification documentation is compiled and submitted with the health and building review package, so the inspector can verify each unit rather than asking you to prove it after installation.
Yes. Beyond a standard cooking line we regularly source walk-in coolers and freezers built to the room, custom stainless fabrication, food packaging and portioning equipment, bakery ovens and proofers, and production machinery for facilities that manufacture rather than serve. Specialized machinery usually has long lead times and non-standard utility demands, so we lock the spec early and design the electrical service, floor loading, drainage, and ventilation around it. Where a unit requires a Canadian field evaluation before it can be energized, we identify that at the sourcing stage instead of on the day of inspection.
Size it from your menu and delivery frequency rather than from square footage. Work out how many days of stock you need to hold, how often your suppliers actually deliver, and how much of that has to be refrigerated rather than frozen or dry. Two deliveries a week needs far more cold storage than five. Undersizing is the more common mistake and the more expensive one to fix, because the box is built into the room and the refrigeration is sized to it. Sizing and specifying a walk-in works through the delivery maths and the shelving geometry that sets the box dimensions.
A convection oven moves hot dry air and is the cheaper, simpler choice for baking, roasting and general production. A combi adds controlled steam, which lets one unit roast, steam, braise, hold and regenerate — real flexibility if your menu needs it, and real cost if it does not. A combi also needs water treatment, a drain and usually more power, so the decision changes your mechanical drawings, not just your equipment budget.
Self-contained units carry their compressor on board: cheaper, simpler, and they dump heat and noise into the room they stand in. Remote systems put the condensing unit outside or on the roof, which keeps heat and noise out of the kitchen and usually lasts longer, at a higher install cost and with refrigerant lines that have to be routed. Rooms with several large boxes, or with no tolerance for added heat load, generally justify remote. The full trade-off, including the roof penetration and electrical implications, is in sizing and specifying a walk-in.
Yes, and this is a common reason a health inspection fails at the end. Food equipment is expected to carry a recognised sanitation certification such as NSF, and anything gas or electrical needs a Canadian certification mark — CSA or another accredited body — to be legally installed here. Equipment bought from outside Canada frequently lacks the Canadian mark even when it looks identical, and an uncertified unit can have to be field-approved or replaced after it is already installed.
Stocked items can ship in days. Custom walk-in boxes, specified hoods, refrigerated cases and anything built to order commonly run six to twelve weeks, and longer if a factory is backed up. Lead time, not construction, is what sets many opening dates, which is why the equipment list should be settled during design rather than after the drawings are approved.
Size on daily production, not on bin capacity, and buy for your busiest day rather than your average. Rated production assumes cool incoming water and a cool room; a hot kitchen in August will produce meaningfully less than the spec sheet. Ice machines also need a drain and, in most Ontario water, some treatment — both of which belong on the plumbing drawings rather than being discovered on install day.
We work with trusted Canadian financing partners who offer lease-to-own and equipment financing programs for food businesses. That lets you keep working capital for inventory, staffing, and the first few months of operation rather than putting it all into stainless steel on day one. Structures vary: full equipment packages, single high-cost items such as refrigeration or a cooking line, and in some cases fit-out costs. Approval, rates, and terms are set by the lender based on your business profile, not by us. We make the introduction, assemble the equipment schedule they need, and coordinate funding with the build schedule.
After the initial consultation and a site visit, you get a written quote broken into design and permitting, construction, and equipment, so you can see where the money actually goes. The number is built from your menu, square footage, and the condition of the space, because a second-generation restaurant with a usable hood and adequate electrical service costs very differently from a cold shell. We flag the variables that move the total most, such as mechanical upgrades, grease interceptor work, and service capacity. No hidden allowances that quietly become change orders later.
Yes. The first consultation is free and it is a working session, not a sales pitch. We review your concept and menu, look at the space or the shortlist of spaces you are considering, and give you an honest read on feasibility, including zoning use, whether the unit can support your ventilation and electrical needs, and what a change-of-use application would involve. You leave with a timeline estimate and a preliminary cost breakdown you can take to a lender or a landlord. Call (226) 336-9954 or email info@nhfc.ca to book one.
We design to the budget rather than designing first and asking you to find the money. Tell us the number early and we will show you where it can be spent to the best effect and where it cannot be cut. Some things are non-negotiable because code requires them: hood and make-up air, grease interceptor, barrier-free washroom access, adequate electrical service. Others are genuinely flexible, including finishes, millwork, seating, and whether certain equipment is new or reconditioned. The goal is a kitchen that passes inspection, runs efficiently, and does not consume the capital you need to open.
A second-generation restaurant space typically runs about $150 to $330 per square foot, a cold shell roughly a third higher, and an operating space being refreshed lower. The Greater Toronto Area runs around 14% above the Kitchener–Waterloo band on trades and lead times. These are planning ranges, not quotes — the real number depends on the drawings, the equipment package and what the building turns out to be hiding. Our cost calculator at nhfc.ca/cost-calculator works from the same figures.
The ones that arrive after construction: permit and plan review fees, the deposit and first month on the lease, utility connections or upgrades, insurance, POS and network, smallwares and opening inventory, staff hiring and training before you take a dollar, and rent running during a fit-out you cannot trade from. A construction budget is not an opening budget, and the gap between them is where projects run short.
Often yes, and it is a common way to protect working capital. Equipment leasing and lease-to-own arrangements treat the equipment as its own asset, which keeps cash available for construction and opening costs. Approval generally turns on the business and the operator rather than the room, so it can move in parallel with the build rather than waiting on it.
A deposit at order is normal, particularly for anything custom or built to order, with the balance due before or on delivery. That matters for cash flow planning because long-lead items have to be ordered early in the project — you are committing money months before the equipment arrives and well before you open.
Four stages. Discover: we review your concept, menu, and site, run the zoning and use check, and produce a budget and timeline. Design: architectural, mechanical, electrical, and equipment layout drawings, coordinated to the Ontario Building Code and your public health unit’s plan review requirements. Build: permits issued, trades mobilized, construction managed through TSSA gas and ESA electrical inspections. Deliver: equipment commissioned, final inspections passed, occupancy granted, keys and documentation handed over. Each stage ends with a decision point where you sign off before we spend money on the next one.
A dedicated NHFC project manager owns your build from permit issuance to handover. They schedule and supervise the trades, chase equipment deliveries against the construction sequence, book the municipal, TSSA, and ESA inspections, and answer to the plans examiner and health inspector on your behalf. They are your single point of contact, so you are not fielding calls from six subcontractors who each need a decision. When a site condition forces a change, the project manager brings you the options and the cost impact before work proceeds, not after the invoice arrives.
You get regular written updates from your project manager covering what was completed, what is scheduled next, where permit and inspection approvals stand, and anything that could affect the opening date. Each stage closes with a milestone review, and you are welcome on site for walkthroughs at the points where they matter most: after rough-in and before walls close, once the hood and make-up air are set, and at equipment commissioning. Photos and inspection records are kept as the project runs, so there is a documented trail rather than a verbal account.
Completion means a full handover, not a set of keys on the counter. Every piece of equipment is tested under load, refrigeration temperatures are verified, and the hood and suppression system are commissioned. Final building, fire, gas, and electrical inspections are closed out and the occupancy permit is in hand before you open. You receive manuals, warranty documentation, as-built drawings, and a maintenance schedule. Post-launch consulting is available for the first weeks of trading, when kitchen workflow, staffing, and equipment settings usually need adjusting against real service volume.
For a typical Ontario project, plan on 14 to 26 weeks from signed lease to opening: roughly 4 to 8 weeks of design and permitting, then 8 to 16 weeks of construction, commissioning and inspections. A second-generation space with usable infrastructure can beat that; a cold shell, a heritage building or a change of use will run longer. The single biggest variable is how long approvals take, which is why they are worth starting the week the lease is signed.
Approvals and long-lead equipment, in that order — rarely the construction itself. A drawing set that does not satisfy plan review comes back with comments and costs weeks; a custom hood or walk-in ordered late holds up everything that follows it. Both are scheduling problems rather than building problems, and both are solved before site work starts rather than during it.
Sometimes, but rarely in the way people hope. Occupancy is granted on the space as a whole, so you cannot usually trade from half a kitchen. What can genuinely be phased is scope that is not needed for occupancy — a patio, a second service area, later seating — provided it is planned that way from the drawings rather than bolted on once the permit is closed.
Across Ontario, most often in Kitchener, Waterloo, Cambridge, Guelph, London, Mississauga and Toronto. Those are the markets we work in most, not the limit of where we go — page nhfc.ca/locations sets out which public health unit and which municipal building department you are dealing with in each. If your project is somewhere else in Ontario, tell us the address and we will come back with the authorities involved and what that combination usually means for the schedule.
The Building Code is provincial, but who reviews your project is not. Kitchener, Waterloo and Cambridge share Region of Waterloo Public Health; Guelph answers to Wellington-Dufferin-Guelph Public Health twenty minutes away; London is Middlesex-London; Mississauga is Peel, which requires notice at least 14 days before opening and before renovation construction starts; Toronto Public Health runs its own plan submission and pre-opening inspection. The building permit is separate again and comes from the municipality.
Yes. Plenty of projects come to us with drawings already done or a contractor already chosen, and we take the parts that are still open — permits, equipment, construction management, or all of the remainder. What we will not do is pretend a drawing set works when it does not; if what you have will not survive plan review or does not match the equipment, we will say so before you spend on it.
No. The six services stand alone and plenty of clients take one or two. Turnkey is how most of our projects run because it is the only version where nobody can point at another vendor when something slips, but it is an option rather than a condition.
For a useful first conversation: the unit address or the shortlist you are considering, the draft lease or offer if one exists, your menu or the closest draft, expected covers and service hours, and the date the money actually lands. With those we can tell you whether the space works, roughly what it costs and how long it takes — and where it does not work, we would rather say so before you sign.
Ask it on the free consultation. You will get a straight answer, including when the answer is that your project needs something we have not listed here.